Tuesday, 15 July 2014

Climate change, hospitals and patient well-being



Dr. Chris Iddon of SE Controls
Comment on hospital overheating from The Climate Change Commission report


The recently reported issue of climate change causing overheating in hospitals with an associated increase in related deaths, not only highlights the risk to patient health from high temperatures and inadequate ventilation, but also questions current thinking on building design.

According to findings from forthcoming research by Cambridge University, headed by Professor Alan Short, around 90% of UK hospital wards are of a design type that makes them susceptible to overheating.

Extracts from the report released by the Climate Change Commission, led by Lord Krebs, indicate that building design and construction are key contributory factors to the overheating and patient health issue. In addition, the Commission has already suggested that the retro-fitting of air-conditioning plant would be uneconomic, so the immediate focus is already centred on cost effective and energy efficient measures of addressing the problem, such as natural ventilation.

While hospital overheating can be readily managed with natural ventilation solutions, the additional benefits, particularly in hospital wards, is that it can also reduce the build up of pathogens, viruses and associated infections by encouraging air movement and ‘flushing’ stale air from the building. Independent research undertaken by Dr. Cath Noakes of Leeds University shows that when windows are closed to reduce heat losses and energy costs, there is an increased risk of infection due to a four-fold increase in airborne pathogens.

Although air quality in critical health and clinical areas of hospitals needs to be of the highest standard, these principles, in many instances, have been compromised in other parts of hospital design. In pre-operation, recovery and general wards, the opportunity for ventilation is often limited to a 100mm wide strip of open window - a limit governed by essential risk directives to protect patients from harm and provide a safe environment.

However, simple modifications could readily be implemented to the ventilation solution, such as high-level vents or window opening, which would to not only maintain patient safety, but also provide adequate ventilation to manage temperatures and improve indoor airquality.

When the lack of cooling is linked to other building design issues, such as south facing glazing, low ceilings, thin walls and the cumulative heat build up from multi-storey structures, there will be and inevitable impact on hospital temperatures

Temperature data research and analysis that I have undertaken with Professor Kevin Lomas, as part of the wider Cambridge University team lead by Professor Short, reveals that in numerous hospital wards across the UK there are number of key factors influencing overheating risk. The work has not only highlighted the resilience of traditional, heavyweight ‘Nightingale wards’ to overheating, but also indicated that solar gain is the key cause of internal temperature increase.

Alongside improved ventilation and increased air movement through carefully planned vents to maintain patient safety, the introduction of measures to limit heat gain, such as the deployment of external shading devices will help reduce overheating risk.

Hospital overheating is a very real issue and this report highlights that most are not only incapable of dealing with any predicted gradual increase in temperatures that may result from climate change, but are also likely to be susceptible to heatwaves.

The links between building design practice and how regulations will need to evolve to manage overheating and assist infection control are likely to be a key outcomes from the research, which will impact all aspects of architecture and construction.

While some retro-fitted solutions can provide effective answers to overheating, the time to review building design standards, specifications and regulations, particularly for future hospital construction projects, is probably already here.


SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling
+44 (0)1543 443060.


Monday, 23 June 2014

Innovative natural ventilation from SE Controls helps keep pupils alert



A new £2 million science centre at Moreton Hall School in Oswestry, is using an advanced NVLogiQ naturalventilation monitoring and control solution from SE Controls to maintain classroom indoor air quality while providing a stimulating and comfortable environment for pupils.

Founded more than 100 years ago, Moreton Hall is one of the UK’s highest achieving independent schools, providing education for girls from age 3 to 18 and boys from 3 to 11, together with accommodation and facilities for boarding.

The new two-storey science building provides high quality teaching laboratories for the school’s junior science, GCSE and A level students and was designed by Shrewsbury based architects, Baart Harries Newall who were keen to ensure that the building’s indoor air quality was maintained within national standards and its energy consumption was minimised.

To achieve the designer’s objectives, SE Controls worked closely with the architects and main contractors, Jones Brothers Weston Rhyn, to develop an assisted natural ventilation solution. Using compact NVLogiQ room controllers linked to automatic opening windows and a low energy cross flow fan in each of the eight lab classrooms, the system manages ventilation as well as the operation of radiators to provide a fully integrated low energy system.

The NVLogiQ room controllers constantly monitor carbon dioxide (CO2) levels in each classroom alongside indoor air temperature and relative humidity, as well as outside temperature, wind and rain via external sensors. Each NVLogiQ unit also incorporates an integral data logger to allow the recording and analysis of all key aspects of the room environment.

The sophisticated monitoring and control algorithm used within the compact NVLogiQ system was developed in conjunction with Loughborough University’s School of Civil and Building Engineering to ensure indoor CO2 levels and temperatures are precisely controlled while minimising building energy losses.

In addition to the eight NVLogiQ controllers and PSUs, 18 SECO N 24 40 400N twin chain compact actuators were also installed by SE Controls together with PIR finger trap sensors and all the appropriate cabling to control the automatic opening of windows and the small cross flow fans in each lab.

During normal operation, as CO2 levels increase within each individual science lab, the NVLogiQ controller triggers SE Controls’ SECO N 24 40 compact chain actuators to begin the incremental opening of the windows to allow fresh air to enter the classroom. Simultaneously, small dampers located on the wall opposite the windows are signalled to open and the low energy fans start to draw air from the room to stimulate cross flow and aid ventilation.


Dr. Chris Iddon, SE Controls’ Design Manager, explained: “There are already a significant number of high quality studies that have identified a clear link between increased internal CO2 levels and a reduction in the ability of students to learn and perform optimally.”

He added: “Post occupancy monitoring of the Moreton Hall classroom environment has shown excellent indoor air quality proving that the design is an example of how having a clearly defined, controlled and executed ventilation strategy can maintain a high quality and stimulating classroom environment for students. Using NVlogiQ enables excellent on demand ventilation whilst minimising heating energy demand.”  


SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling

 +44 (0) 1543 443060.

Friday, 21 March 2014

SE Controls Provides a Breath of Fresh Air for Jubilee House



Indoor air quality at a new £3 million energy efficient office development for the Diocese of Southwell & Nottingham, is being monitored and controlled by an advanced NVLogiQ natural ventilation system from international smoke and natural ventilation specialist, SE Controls.
                               
The new 1290m2 Jubilee House building was designed by Nottingham based, Maber Associates and provides the diocese with a mission centre, conference facilities and a new administration centre for approximately 50 staff who were previously located in the adjacent Grade II listed Dunham House.

The BREEAM Excellent rated building incorporates a number of energy saving features including high levels of insulation and natural daylight alongside low energy light fittings and SE Controls’ efficient natural ventilation system, which monitors, manages and controls carbon dioxide (CO2) levels and temperature to maintain a comfortable indoor environment.

The adaptive natural ventilation solution developed, installed and commissioned by SE Controls uses 26 of its innovative NVLogiQ controllers, which constantly monitor the air quality in 24 separate zones. This provides a highly versatile system that not only allows the indoor air quality and ventilation to be managed locally in each zone, but every NVLogiQ unit is also linked together as a networked building solution.

Depending on the level of CO2 present in each zone, alongside information about temperature and humidity, each NVLoqiQ controller signals a series of dedicated NVLogiQ PSU (power supply units) to automatically open windows and rooflight vents, allowing stale hot air to be replaced with cooler fresh air using the thermal stacking effect.

The sophisticated monitoring and control algorithms used in the NVLogiQ controller were developed in conjunction Loughborough University’s Building Energy Research Group and are designed to not only provide highly accurate indoor air quality management and ventilation, but also minimise energy losses from the building.




Every compact NVLogiQ controller, which measures 160mm x 105mm, also incorporates a data logger, which allows the indoor air quality, building performance and ventilation strategy to be constantly recorded for analysis, enabling the operational parameters for each zone in Jubilee House to be tuned to meet specific environment needs.

In addition to the NVLogiQ controllers and PSUs, SE Controls also provided 50 SECO N 24 40 compact chain actuators to precisely control the opening and closing of the building’s windows and rooflight vents, which are also linked to external temperature, wind and rain sensors.

In the event of rain, the system automatically closes all rooflights fully and reduces the window opening to 10%, yet authorised personnel can also adjust the individual ventilation strategy for each zone directly from the front panel of each NVLogiQ controller. A temporary over-ride facility is also available from the front panel, which allows a zone’s system to be controlled manually.

SE Controls project leader on Jubilee House, Majeed Mohammed, explained: “NVLogiQ is an ideal solution for Jubilee House as it provides optimised indoor air quality, localised monitoring and control in 24 zones and constant real time data logging to enable the building performance to be monitored and tailored.”

He added: “Ultimately, however, the natural ventilation system is about ensuring the building’s occupants have a comfortable working environment while minimising the building’s energy consumption. This solution not only meets these requirements, but also provides a level of adaptability and control that is often difficult to achieve using alternative methods.”
  
SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling

 +44 (0) 1543 443060.

Wednesday, 12 March 2014

SE Controls Smoke and Natural ventilation solution for Airbus



A new 25,000m2 office building for leading aircraft manufacturer, Airbus, is using an advanced smoke and natural ventilation system from SE Controls to provide a comfortable working environment for staff while ensuring that an effective smoke and fire control strategy can be implemented in the event of a fire.

The four storey building, which is part of the £70 million Airbus Aerospace Business Park development at Filton, accommodates more than 2,500 staff and brings together engineering, design and customer support functions that are currently located in several smaller buildings onsite into the new engineering and technology campus.

SE Controls was involved in the project from the early stages to clarify the ventilation strategy and provide calculations on the free area requirements for the smoke vents to ensure compliance and performance standards were met.

Four separate atrium spaces feature as part of the building, designed by AWW Architects, and each incorporates 84 Schüco AWS 102 projected top hung vents. The vents are automatically operated by a total of 336 SCCO 24 30 concealed actuators, which were supplied, installed and commissioned by SE Controls in partnership with specialist façade contractor, Norking Aluminium.

In addition to installing the actuators, the interface control panels were also supplied, installed and commissioned by SE Controls together with the fire rated cabling, which is completely concealed within the curtain walling.

During day-to-day operation, the natural ventilation system responds to signals from sensors linked to the building management system (BMS) to ensure that the indoor air quality and temperature are maintained within the pre-set parameters to maintain a comfortable working environment.

In the event of a fire, the building’s alarm system signals the natural ventilation system to automatically close all the vents as part of the smoke and fire control strategy. This not only restricts the flow of oxygen into the building to help suppress the fire but also allows precise control to be taken by fire officers via the system’s manual control points, enabling smoke to be cleared from the relevant atrium.

As SE Controls’ actuators and Schüco vents have been tested and proven to meet the European smoke vent standard hEN12101-2 and the Construction Products Regulations that came into force in July 2013, the ventilations system is CE marked and fully compliant.

SE Controls’ Commercial Director, Martin Oates, commented: “The Airbus project is an excellent example of how a fully compliant life safety critical smoke ventilation system can also be utilised on a day to day basis to provide a controlled natural ventilation solution that maintains comfort for Airbus staff.”

He added: “By being brought into the process at a very early stage, we were able to clarify the specification, assist the design team and help resolve any technical and operational issues during the build.”  
  
SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling

 +44 (0) 1543 443060.

Tuesday, 10 December 2013

MP, MICHAEL FABRICANT OPENS SE CONTROLS’ NEW TECHNICAL INNOVATION CENTRE



Lichfield’s Member of Parliament, Michael Fabricant, today officially named and opened the new technical innovation centre as part of a business and industry focused visit to one of the region’s fastest growing businesses, SE Controls.

The 21,500 sq.ft (2000 sq.mtr) ‘Hood innovation Centre’ is named posthumously in honour of the company’s former Head of R&D, Chris Hood, who played a pivotal role in developing SE Controls’ smoke and natural ventilation system products, which have helped the company grow by more than 35% since 2010 and create around 25 new jobs over the past two years.

“Product development and technical innovation are essential facets of our business and helps ensure that we provide the best and most effective solutions possible. This not only helps us maintain a strong competitive advantage, but is also vitally important when designing and manufacturing life critical smoke ventilation systems,” explained SE Controls’ Managing Director, Will Perkins.

He added: “Chris Hood was a true innovator and was instrumental in many of the products, systems and solutions that we offer today, so it’s very fitting that his legacy is recognised and acknowledged with the dedication of our new technical innovation centre in his name.”


SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling +44 (0) 1543 443060.

Wednesday, 30 October 2013

SE Controls helps create a stimulating learning environment at Passmores Academy


Passmores Academy in Harlow is using a natural ventilation system from leading smoke and natural ventilation specialist, SE Controls, to provide a comfortable and stimulating learning environment for pupils while helping to reduce the school’s carbon footprint.

Designed by Jestico & Whiles and constructed by Wilmott Dixon, the £23 million school provides places for 1200 students and uses an innovative design where five arms radiate from a 2.5 storey elliptical atrium ‘hub’, allowing access to the flexible teaching facilities and recreation areas from the common central area.

A range of low impact design features and sustainable technologies have been incorporated in the BREEAM ‘Very Good’ rated school, including solar shading, biomass boilers and energy efficient glazing together with the use of a natural ventilation strategy to improve and mange indoor air quality while reducing the need for mechanical cooling.

To provide the level of control and flexibility required for the school’s natural ventilation system to operate effectively within the pre-defined set points, SE Controls supplied and installed 7 OS2 control panels to operate the rooflights, atrium louvres and entrance screens.

In addition, the company also supplied and installed the rooflight and window actuators through specialist glazing contractor, English Architectural Glazing and were responsible for commissioning the complete natural ventilation system, which is interfaced with the school’s building management and fire safety system.

SE Controls’ Project Manager, Darren Wainwright, explained: “Indoor air quality in schools is a vital consideration as it not only manages the temperature within the building, but more importantly, the level of carbon dioxide present, which has been proven to reduce learning ability if it exceeds pre-defined national guidelines. Even the classrooms have CO2 monitors fitted so that the level can be monitored and windows can be manually opened, if required.”

He added: “By incorporating natural ventilation and linking our control panels to the BMS, Passmores Academy can not only ensure that the air quality and environment is effectively managed but also that the energy costs are kept in check.”   

SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling
+44 (0) 1543 443060.


Monday, 7 October 2013

Precision Ventilation Control for Sheffield University NAMRC



Precision window actuators from SE Controls are being used as part of an energy efficient natural ventilation system at Sheffield University’s Nuclear Advanced Manufacturing Research Centre (NAMRC) in Rotherham, to help maintain a comfortable environment for researchers and staff.

Work at the NAMRC focuses specifically on innovative research into metals and manufacturing engineering, rather than radioactive research and the new BREEAM Excellent rated building, which was designed by Bond Bryan Architects, is based around an open plan 5,000 m2 workshop that incorporates cutting edge manufacturing equipment and facilities.

As the building already employs low energy and renewable initiatives, such as 320kW ground source heat pumps and a 900kW wind turbine, the use of natural ventilation was an ideal solution, as the temperature and air quality can be maintained within clearly defined set points while minimising the need for additional mechanical cooling.

To provide the high degree of control required, SE Controls, supplied, installed and commissioned a range of chain actuators, which are linked to the NAMRC building management system and are used to control the operation of the high and low level vents.

Twenty TGCO 24 15 actuators with a 350mm stroke length were installed on the building’s high level exhaust vents, while the need to protect against finger entrapment on the low level louvres prompted the selection of eighteen SE Controls’ TGCO 24 20 ‘Easi-Drive’ compact actuators each with 160mm stroke length.

SE Controls’ Project Manager, Darren Wainwright, explained: “It is absolutely vital that the natural ventilation strategy and system perform as designed to allow the right amount of fresh air to enter the building while ensuring that heat energy is not lost unnecessarily during the process. By using precision actuators to provide incremental operation of the system’s vents and louvres, it helps ensure that required performance is within the specified design parameters.”

SE Controls specialises in the design, project management and installation of advanced smoke ventilation and natural ventilation solutions to meet the needs of architects, contractors, building services engineers and facilities managers worldwide. Further information on SE Controls’ products, solutions and projects can be obtained by visiting www.secontrols.com or calling

+44 (0) 1543 443060.